Russell Exit from I-15 South to Close for Two Weeks

Russell Exit from I-15 South to Close for Two Weeks

The I-15 Design-Build project continues its slow progress, resulting in the upcoming closure of a key I-15 ramp for two weeks.

The ramp from southbound I-15 to Russell Road will be closed from Sunday, May 15 through Thursday, May 26 for construction. This is an all-day closure. Detour routes are I-15 southbound to Tropicana Ave. and westbound I-215 to Decatur Blvd. north to Russell Road.

Additionally:

  • The ramp from eastbound I-215 to Las Vegas Blvd. will be closed from Sunday, May 8 through Wednesday, May 11 from 9 p.m. to 5 a.m. for bridge work.

 

  • The ramp from southbound I-15 to Las Vegas Blvd. will be closed on  Tuesday, May 10 and Wednesday, May 11 from 9 p.m. to 5 a.m. for bridge work.

 

  • The ramp from southbound I-15 to eastbound I-215 will be closed on Thursday, May 12 from 9 p.m. to 5 a.m.

Sewer Work Restricts Travel on Eastern, Tropicana

Sewer Work Restricts Travel on Eastern, Tropicana

The Clark County Water Reclamation District (District) announced lane restrictions from May 2 through at least June 30 as part of a sewer rehabilitation project on Eastern Avenue.              

Northbound Eastern Avenue traffic will be reduced to two travel lanes from north of Reno Avenue through the intersection at Tropicana Avenue. Eastbound Tropicana Avenue traffic will be reduced to two travel lanes from west of Burnham Avenue to Topaz Street. One left-turn lane from westbound Tropicana Avenue to southbound Eastern Avenue will be restricted. Access to driveways will be maintained.

Work on Eastern Avenue and Tropicana Avenue will be conducted Sunday through Thursday, 9 p.m. to 5:30 a.m.

More Closures, Delays Expected from I-15/215 Work

More Closures, Delays Expected from I-15/215 Work

Continuing work on the I-15 Design-Build South project will cause the following closures and potential delays in the coming week:

  • The I-15 southbound to I-215 eastbound ramp will be reduced to one lane from Sunday, April 24 through Sunday, May 1. These are all-day lane restrictions. Major traffic delays are expected.
  • The I-15 northbound to I-215 westbound ramp will be closed on Monday, April 25 and Tuesday, April 26 from 9 p.m. to 5 a.m. for roadway reconfiguration.
  • The Las Vegas Boulevard to I-215 westbound ramp will be closed on Monday, April 25 and Tuesday, April 26 from 9 p.m. to 5 a.m. for roadway reconfiguration.
  • On Sunday, May 1, traffic from I-15 southbound to I-215 eastbound and westbound will use the new off-ramp.

Ramp Closures for Construction Wednesday Night on I-15

Ramp Closures for Construction Wednesday Night on I-15

Continuing construction work on the I-15 Design-Build South project will cause closures and potential delays tonight.

  • The off-ramp from northbound I-15 to Russell Road will be closed from 9 p.m. to 5 a.m. for prep work to open the Frank Sinatra access ramp.
  • The ramp from northbound I-15 to Blue Diamond Road will be closed from 9 p.m. to 5 a.m. to pour concrete barrier rail.
  • The southbound I-15 to westbound I-215 ramp will open on Thursday at 5 a.m. The new ramp exit from southbound I-15 will be 500 feet north of Sunset Road.

Traffic Restricted on Circus Circus Drive

Traffic Restricted on Circus Circus Drive

The Clark County Water Reclamation District is announcing lane restrictions as part of a sewer rehabilitation project on Circus Circus Drive. These restrictions are expected to last at least a month.

The two center lanes on Circus Circus Drive will be restricted.  Driveway access will be controlled.  The outside eastbound and westbound lanes will remain open. Access to Circus Circus Drive from both northbound and southbound Las Vegas Boulevard South will be controlled.     

Work on Circus Circus Drive will be conducted Monday through Thursday, 6 a.m. to 6 p.m. and on Fridays from 6 a.m. to noon, on Industrial Road Sunday through Friday, 9 p.m. to 6 a.m., and on Las Vegas Boulevard Monday through Friday, 2 a.m.

Blue Diamond Delays Expected Monday from Construction Work

Blue Diamond Delays Expected Monday from Construction Work

As part of the I-15 Design-Build South project, crews will begin pouring concrete Monday for the new Blue Diamond direct-connect flyover ramp that will bring traffic from eastbound Blue Diamond Road to northbound Interstate 15.

During the concrete pour, the following closures and lane shifts are scheduled. Motorists are advised to avoid the area during these times as significant delays are expected.

4 p.m. - 11 p.m.        Intermittent alternating lane shifts on I-15 on-ramp to Blue Diamond Road

7 p.m. - 5 a.m.          Lane closures on Southbound I-15 at Blue Diamond Road

8 p.m. - 5 a.m.          Various lane closures on northbound I-15 at Blue Diamond Road

9 p.m.

Viva Bike Vegas Registration Open

Viva Bike Vegas Registration Open

Cycling enthusiasts in Nevada and across the country are invited to join the Regional Transportation Commission of Southern Nevada (RTC) for Viva Bike Vegas 2011 on Saturday, Oct. 15.

This year, all riders will have the unique opportunity to bike the bright lights of the world-famous Las Vegas Strip. The fourth annual cycling event will feature three spectacular routes for cyclists of all skill levels, including a 103-mile century ride, as well as 60-mile and 17-mile routes. Century riders will travel from the Las Vegas Strip to the vistas of the Red Rock Canyon National Conservation Area and the scenic trails near Lake Mead National Park.

Riders can register for any of the three routes for only $85 until May 14. Pricing increases thereafter. Online registration is open at www.vivabikevegas.com.